Implementation Process Plan (Gantt Chart)

ISO QMS Implementation Process Plan (Gantt Chart)
(Less Resources, Task Details, Task Links and Time Lines)

Task Name (This plan shows only the top-level tasks in each phase) Resource Names Duration Start Finish
         
OVERALL TIME ESTIMATE TO COMPLETE ISO 9001:2015 QMS PROJECT   93 d 01 Mar '17 07 Jul '17
Continuous Education and Training (Educate Company Wide) - 83 d 01 Mar '17 23 Jun '17
Define the employee’s role in the ISO QMS - 4 h 01 Mar '17 01 Mar '17
Schedule meetings with supervisors to educate on ISO based program - 4 h 01 Mar '17 01 Mar '17
Schedule meetings with employees to educate on ISO based program - 82 d 02 Mar '17 23 Jun '17
         
PHASE 1 Preparation for ISO Based Quality Program   21 d 01 Mar '17 29 Mar '17
Project Strategy & Start Up Tasks I Q C 21 d 01 Mar '17 29 Mar '17
         
PHASE 2 Develop Core Elements, Policies, Procedures & Work Instructions   19 d 30 Mar '17 25 Apr '17
Section # 4.3, Quality Manual - Document Permissible Exclusions with Justifications - 1 d 30 Mar '17 30 Mar '17
Section # 7.5 Documented Information - 17 d 30 Mar '17 21 Apr '17
Section # 5.1 Leadership and Commitment - 13 d 30 Mar '17 17 Apr '17
Section # 4.0, Context of the Organization - 15 d 30 Mar '17 19 Apr '17
Section # 5.2, Quality Policy - 3 d 30 Mar '17 03 Apr '17
Section # 6.2, Quality Objectives - 5 d 30 Mar '17 05 Apr '17
Section 7.1, Resources - 12 d 30 Mar '17 14 Apr '17
Section 7.2, Competence and Awareness - 19 d 30 Mar '17 25 Apr '17
Section # 10.2, Nonconformity and Corrective Actions - 17 d 30 Mar '17 21 Apr '17
         
PHASE 3 Auditor, Audit Requirements, Selection and Training   14 d 26 Apr '17 15 May '17
Selecting and educating internal auditors - 4 d 26 Apr '17 01 May '17
Train internal auditors (12 - 16 hrs.) I Q C 5 d 26 Apr '17 02 May '17
Section # 9.2, Internal Audit - 14 d 26 Apr '17 15 May '17
Registrars and Selection - 8 d 26 Apr '17 05 May '17
Audit all documents implemented during Phase 2 - 5 d 26 Apr '17 02 May '17
Review Phase 3 for Completion - Management Review - 4 h 03 May '17 03 May '17
         
PHASE 4 Develop Policies, Procedures and Work Instructions   20 d 16 May '17 12 Jun '17
Quality Manual (Miscellaneous) - 7 d 16 May '17 24 May '17
Section # 6.0 Planning - address risks, and QMS changes - 14 d 16 May '17 02 Jun '17
Section # 7.1.5, Control of Monitoring and Measuring Equipment - 12 d 16 May '17 31 May '17
Section 7.4, Communication - 12 d 16 May '17 31 May '17
Section # 8.1, Operational Planning and Control - 12 d 16May ‘17 31May “17
Section # 8.2, Customer Related Processes - 16 d 16 May '17 06 Jun '17
Section # 8.3 Design & Development - 20 d 16 May '17 12 Jun '17
Section # 8.4, Control of External Providers - 14 d 16 May '17 02 Jun '17
Section # 9.1.3, Analysis and Evaluation - 9 d 16 May '17 26 May '17
Section # 9.1.4 Root Cause Analysis - 8 d 16 May '17 25 May '17
Audit all documents implemented during Phase 4 - 4 d 16 May '17 19 May '17
         
PHASE 5 Develop Remaining Policies, Procedures & Work Instructions   19 d 13 Jun '17 07 Jul '17
Section 8.5.1, Control of Production and Service Provision - 19 d 13 Jun '17 07 Jul '17
Section # 8.5.2 Identification and Traceability - 9 d 13 Jun '17 23 Jun '17
Section 8.5.4, Preservation - 14 d 13 Jun '17 30 Jun '17
Section # 8.7, Control of nonconforming Product - 11 d 13 Jun '17 27 Jun '17
Section 9.1.2, Customer Satisfaction - 14 d 13 Jun '17 30 Jun '17
Section # 9.3 Management Review - 10 d 13 Jun '17 26 Jun '17
Section # 10.3, Continuous Improvement - 11 d 13 Jun '17 27 Jun '17
Audit all documents implemented during Phase 4 - 4 d 13 Jun '17 16 Jun '17
         
PHASE 6 Audits, Status Meetings   6 d 10 Jul '17 17 Jul '17
Progress meeting - 6 d 10 Jul '17 17 Jul '17
Home   •   What & Why   •   Benefits   •   Quality for Profit   •   Implementation   •   Biography   •   Contact

© 2017 ISO Quality Consulting. All Rights Reserved.
Website Design and Hosting by Radical Webs Inc. Fort Lauderdale, Florida